Business Process: Risk Management

START
  |
  |- [Task: 1000] Risk Identification
  |   Team: Risk Owner (Operational Unit)
  |   Description:
  |   A potential risk has been identified within an operational unit. The Risk Owner captures basic data (Category, Description, Early Warning Indicators) to initiate the process in accordance with KonTraG.
  |   |-- [Event: 10] Submit Proposal (Forward to Central Risk Management) --> [Task: 1100] Validation
  |   |-- [Event: 20] Discard (Draft deleted) --> [Task: 1990] Deleted
  |
  |- [Task: 1100] Validation
  |   Team: Central Risk Management
  |   Description:
  |   Central function checks if the identified issued qualifies as a relevant risk or if it is a duplicate.
  |   |-- [Event: 10] Confirm Risk (Risk is valid, proceed to assessment) --> [Task: 1200] Gross Assessment
  |   |-- [Event: 20] Reject (Not a risk or duplicate) --> [Task: 1900] Archived
  |   |-- [Event: 30] Request Info (Send back to Owner for details) --> [Task: 1000] Risk Identification
  |
  |- [Task: 1200] Gross Assessment
  |   Team: Risk Owner (Operational Unit)
  |   Description:
  |   Quantitative assessment of the risk WITHOUT considering planned or existing measures. Impact and Probability are estimated to determine the Gross Risk Score.
  |   |-- [Event: 10] Save Gross Data (Proceed to Measure Definition) --> [Task: 1300] Measure Definition
  |
  |- [Task: 1300] Measure Definition
  |   Team: Risk Owner (Operational Unit)
  |   Description:
  |   Definition of risk mitigating measures (Avoid, Reduce, Transfer, Accept). Documentation of costs and responsibilities for these measures.
  |   |-- [Event: 10] Measures Defined (Proceed to Net Assessment) --> [Task: 1400] Net Assessment
  |   |-- [Event: 20] Update Assessment (Go back to Gross Assessment) --> [Task: 1200] Gross Assessment
  |
  |- [Task: 1400] Net Assessment
  |   Team: Risk Owner (Operational Unit)
  |   Description:
  |   Re-evaluation of Impact and Probability taking the defined measures into account (Residual Risk). Crucial for IDW PS 340 compliance.
  |   |-- [Event: 10] Submit for Aggregation (Forward to Central RM) --> [Task: 1500] Aggregation & Analysis
  |
  |- [Task: 1500] Aggregation & Analysis
  |   Team: Central Risk Management
  |   Description:
  |   The risk is analyzed in the context of the total risk portfolio (Risk Aggregation/Monte Carlo Simulation) to check against the company's Risk Bearing Capacity.
  |   |-- [Event: 10] Approve (Risk within appetite, standard monitoring) --> [Task: 1600] Monitoring
  |   |-- [Event: 20] Insufficient Mitigation (Measures not enough, send back) --> [Task: 1300] Measure Definition
  |   |-- [Event: 30] Critical Escalation (Threat to existence, forward to Board) --> [Task: 1550] Board Review
  |
  |- [Task: 1550] Board Review
  |   Team: Management Board / Risk Committee
  |   Description:
  |   High-level decision required. Risk exceeds risk bearing capacity or is a "bestandsgefährdendes Risiko" (§91 Abs. 2 AktG).
  |   |-- [Event: 10] Accept Risk (Special approval granted) --> [Task: 1600] Monitoring
  |   |-- [Event: 20] Demand Action (Force new measures) --> [Task: 1300] Measure Definition
  |
  |- [Task: 1600] Monitoring
  |   Team: Risk Owner (Operational Unit)
  |   Description:
  |   Continuous surveillance of the risk and the effectiveness of measures. Periodic review (e.g., quarterly).
  |   |-- [Event: 10] Report: No Change (Keep monitoring) --> [Task: 1600] Monitoring
  |   |-- [Event: 20] Risk Changed (Values or measures changed) --> [Task: 1200] Gross Assessment
  |   |-- [Event: 30] Risk Obsolete (Risk no longer exists) --> [Task: 1800] Closure Review
  |
  |- [Task: 1800] Closure Review
  |   Team: Central Risk Management
  |   Description:
  |   Final check if the risk can really be closed.
  |   |-- [Event: 10] Close Risk (Archive) --> [Task: 1900] Archived
  |   |-- [Event: 20] Deny Closure (Keep active) --> [Task: 1600] Monitoring
  |
  |- [Task: 1900] Archived
  |   Team: System
  |   Description:
  |   Risk is closed but kept for audit trails and historical data analysis.
  |   |-- [Event: 10] Reactivate --> [Task: 1100] Validation
  |
END
  |
  |- [Task: 1990] Deleted
  |